1Result summary
Each document in either register is listed below or named in the exception lists in Part 6 of the full report; per-discipline sums equal the totals.
312 graded findings across 312 changed documents. Grades reflect the effect of what is drawn and its indicative cost; they are a reviewer's aid, not a valuation.
2Register comparison
Each row pairs a tender document with its contract counterpart by number, then by title where the number changed. Twelve rows shown of 1,284; the full table is filterable in the report.
| Number | Title | Tender rev / date | Contract rev / date | Result |
|---|---|---|---|---|
| SF-C-A-0001 | Drawing list and cover sheet | P0306 Mar 2026 | C0122 Jun 2026 | Revision raised P03 to C01 |
| SF-C-A-1001 | Site plan | P0206 Mar 2026 | C0122 Jun 2026 | Revision raised P02 to C01 |
| SF-C-A-2100 | Podium ground floor plan | P0206 Mar 2026 | C0122 Jun 2026 | Revision raised P02 to C01; 14 drawn differences |
| SF-C-A-2103 | Level 3 floor plan, typical | P0206 Mar 2026 | C0222 Jun 2026 | Revision raised P02 to C02; 3 drawn differences |
| SF-C-A-2114 | Roof and plant plan | P0106 Mar 2026 | C0122 Jun 2026 | Title changed from "Roof plan" |
| SF-C-A-3001 | Elevations north and east | P0206 Mar 2026 | C0122 Jun 2026 | Revision raised P02 to C01 |
| SF-C-A-4002 | Section B-B | P0206 Mar 2026 | C0122 Jun 2026 | Revision raised P02 to C01; content unchanged |
| SF-C-A-5120 | Door schedule | P0206 Mar 2026 | C0222 Jun 2026 | Revision raised P02 to C02; 6 rows changed |
| SF-C-A-5301 | Wall types | P0106 Mar 2026 | C0122 Jun 2026 | Revision raised P01 to C01; type W-12 rating changed |
| SF-C-A-6210 | Lift lobby details, typical | not in tender | C0122 Jun 2026 | Added in contract |
| SF-C-A-2103A | Level 3 ceiling plan | P0106 Mar 2026 | not in contract | Superseded by SF-C-A-2203 |
| SF-C-A-2203 | Level 3 reflected ceiling plan | not in tender | C0122 Jun 2026 | Added in contract; supersedes SF-C-A-2103A |
| Dates are the drawing dates in the title blocks. Register issue dates: 12 March 2026 (tender), 29 June 2026 (contract). | ||||
3Drawing comparison
SF-C-A-2103, Level 3 floor plan, typical. Excerpt at grids C to E / 3 to 5, apartments 3.05 and 3.06 with the central corridor. Tender issue on the left, contract issue on the right; removed or moved elements are shown dashed on the contract crop.
- Contract issue, as drawn
- Tender position, removed or moved
- Structural grid
- Finding, numbered below
-
MajorDoor D-07 relocated; corridor narrowedDoor D-07 relocated 600 mm east; corridor 3.01 south wall moved 450 mm north between grids C and E; corridor width reduced from 1,600 mm to 1,150 mm. Door schedule SF-C-A-5120 row D-07 is unchanged. Clear width at the door approach and the accessible route to lobby 3.02 to be confirmed by the designer.
-
MediumWall W-12 extended to grid 5Wall W-12 extended 1,800 mm south to meet the party wall at grid 5, enclosing store 3.07 on four sides. Wall type W-12 now shown as a 60-minute rated partition on SF-C-A-5301; the Level 3 plan hatch still reads as 90 minutes. Repeats on eleven typical floors.
-
MinorRoom name changedRoom 3.02 renamed from "Lobby" to "Lift lobby". Tag text only; no change to the drawn enclosure, finish or door set. Matches the new sheet SF-C-A-6210, Lift lobby details.
Dimensions are scaled from the drawings and rounded to 50 mm; they indicate the order of the change and are not setting-out dimensions. Grades are indicative, from the drawings alone.
4Specification consistency, contract issue
Within the contract issue, each specification clause that states a drawn or scheduled property is read against the drawing or schedule that shows it. Four of 212 checked clauses shown.
| Clause | Specification states | Drawing or schedule shows | Result |
|---|---|---|---|
| Vol. 2, 4.3.2 | Internal apartment doors: 44 mm solid-core leaf, hardwood lipping. | SF-C-A-5120, row D-07: 44 mm solid-core leaf. | Agrees |
| Vol. 2, 5.1.4 | Corridor partitions type W-12: 60-minute fire resistance, full height to slab. | SF-C-A-5301: W-12 at 60 minutes. SF-C-A-2103 C02: W-12 hatched as 90 minutes. | Discrepancy between plan and wall-type sheet |
| Vol. 3, 2.2.1 | Corridor floor finish: sheet vinyl, 2.0 mm, slip resistance class as scheduled. | Finishes schedule SF-C-A-5410, room 3.01: vinyl 2.0 mm. | Agrees |
| Vol. 2, 4.6.3 | Apartment entrance doors: lever handles throughout, accessible pattern. | SF-C-A-5120, row D-07 hardware set H-3: knob set. | Discrepancy between clause and schedule |
Consistency is checked within one issue only. A discrepancy is reported as found; which document governs is a matter for the contract, not for this report.
5What this report does and does not say
It does say
Which documents exist in each issue, how each one was paired, and what changed between them as drawn, scheduled or written. Each change is named by element, located by grid and level, and graded for its effect and indicative cost. Every document that could not be compared is listed with the reason.
It does not say
Whether a change is correct, approved or priced. Dimensions are scaled from drawings, not measured on site. Grades are a reviewer's aid for ordering attention, not a valuation or an instruction. Where a clause and a drawing disagree, the report records the disagreement; it does not decide which governs.